City officials will answer questions and provide information regarding the Taft Dock renovation project from 4-6 p.m. Wednesday at the Taft 51st Street Park.
The $450,000 project to make needed repairs on the dock will begin Monday, Sept. 17. At that time, there will be no access to the dock. The project is scheduled to be completed by Nov. 9.
The project includes upgrading the dock by replacing the two piles, replacing the substructure beneath the deck, installing plastic lumber for decking and rails, and bringing the dock up to American Disabilities Act and other miscellaneous safety standards.
For further information, go to the Lincoln City’s webpage, www.lincolncity.org. or call the Public Works Department at 541-996-2154.